Chinese-funded project delivers 260 boreholes in Plateaux region

Social
Tuesday, 05 May 2026 18:45
Chinese-funded project delivers 260 boreholes in Plateaux region

(Togo First) - A Chinese-funded borehole construction project in Togo's Plateaux region had completed 260 of its 305 planned water points as of April 30, 2026, according to a field monitoring mission.

The monitoring team, made up of Chinese and Togolese technical experts, said the remaining 45 boreholes are in the final stages of completion. Launched in December 2024 for a two-year period, the project is progressing at a strong pace.

This tour allows us to observe significant progress. We remain committed to delivering reliable, long-lasting infrastructure that meets the expectations of local communities,” said Huang Xianzhou, head of the rural hydraulics project in Togo. He said the works would be fully completed by June 2026.

The boreholes completed so far are spread across nine prefectures in the Plateaux region: Anié, Est-Mono, Haho, Moyen-Mono, Ogou, Amou, Kloto, Kpélé and Agou.

The project is part of broader efforts to expand access to drinking water in rural areas. It is being implemented as part of Sino-Togolese cooperation, aimed at sustainably improving living conditions in local communities.