Costs of construction permit lowered to ensure buildings are well built

Economic governance
Wednesday, 06 June 2018 16:22
Costs of construction permit lowered to ensure buildings are well built

(Togo First) - Beside the reduction of the cost of construction permit, automation of issuance processes of this permit are the main reforms initiated by Togolese government to improve its business environment and attract investors.

In regards to the permit’s cost, national construction and public works laboratory reduced fee needed for soil survey, for a one/two level warehouse, from Cfa900,000 to Cfa350,000.

As a result, the cost of construction permit for households also sharply dropped, to a minimum of Cfa250,000.

In addition, delay for the permit’s issuance was reduced, and application process was simplified. Indeed, it is now possible to apply from home since the process has been   digitalized. This aligns with the new guidelines of WAEMU regarding actors’ mobility, especially architects.

To this move pairs a greater monitoring of constructions with the reinforcement of capacities in terms of equipment and human resources at concerned administrations. The government wishes through this to make construction safer.

Many other decisions were taken under the decree 2016-043/PR of April 1, 2016. They also positively impact issuance of construction permits. Among others, they relate to insurance policy and other requirements needed to ensure good work quality, etc.