Togo: The renovation of the PIA to Kpomé road is 55% done

Public works
Tuesday, 23 May 2023 15:45
Togo: The renovation of the PIA to Kpomé road is 55% done

(Togo First) - Works to renovate and asphalt the 10 km long road that connects the Adétikopé Industrial Platform (PIA) to its extension zone in Kpomé, are 55% complete.  This was reported during an on-site visit conducted by Zouréhatou Kassah-Traoré, the Togolese minister of public works, on May 19, 2023.

Regarding the deadline of the project, the ministry indicated that 66% of the time allotted has already been consumed. According to reports, earthwork and roadwork, along with the construction of sanitation facilities and a bridge, are underway

Despite the gap between the rate of physical progress and the consumed timeframe, Minister Kassa-Traoré said she is happy with the progress and urged SOGEA-SATOM, the contractor, to speed up its pace so the deadline is met.

The works, once finished, will birth a two-lane road, with each lane having a width of 7m and separated by a 2m divider. Drainage and sanitation facilities like culverts and ditches are also included in the project, as well as a 25m-long artifice (in the form of a bridge) to serve as an underpass for locals.